When does API 653 require a hydrostatic test?
API 653 clause 12.3.1 requires a full hydrostatic test in three cases: the tank was reconstructed; the tank had a major repair or major alteration, unless one of the exemptions in 12.3.3 applies; or an engineering evaluation finds the test is needed because the service has become more severe.
The three cases
- Reconstruction. A tank that was taken apart and rebuilt, on the same site or a new one, is always hydrotested.
- A major repair or major alteration. Clause 3.25 defines these: large shell penetrations or shell plates below the design liquid level, bottom penetrations close to the shell, annular plate replacement, long runs of vertical shell weld or annular radial weld, a new bottom, shell-to-bottom weld work beyond set amounts, jacking the shell, and some nonmetallic repairs. A major repair can avoid the test only through 12.3.3.
- A more severe service. Storing a heavier product (a higher specific gravity raises the shell stress), running the tank colder (see Figure 5.2 on brittle fracture), or putting a damaged tank back in service. Here the test is required when an engineering evaluation says so; it is a judgment, not an automatic trigger.
What does not need a hydrotest
Clause 12.3.4 names two kinds of work that are not major repairs and so do not by themselves call for a test: any repair or alteration to a floating roof, and replacing portions of the bottom outside the critical zone when the subgrade is acceptable to the authorized inspector and the annular ring, or the shell and bottom support in the critical zone, stays intact.
How the test is run
Clause 12.3.2 fills the tank to the level API 650 sets for a new tank, unless the tank condition limits the fill height (API 653 clause 4.3.3.2 gives the hydrotest stress for that check). The level is held for at least twenty-four hours, and the tank is watched during filling for leaks and settlement. Repaired welds above the water line are examined as API 650 requires.
Clause 12.5 adds a settlement survey for existing tanks that are hydrotested, unless the tank has a documented history of acceptable settlement and none is expected during the test. The survey is taken empty first, then during filling and at full test level.
Who decides
All repair work is approved before it starts (clause 9.1.3), and unless a specific section says otherwise, a repair that needs a hydrotest is approved by a storage tank engineer (clause 9.1.4). Whether a repair is major, and whether an exemption applies, is a call for the engineer, the authorized inspector and the owner together, made on the actual scope of work.
The hydrotest decision in TankForge
The repair job card records the hydrostatic test decision with a note, and the draft report carries it in the repair summary with the clause. When the decision is missing on a tank with repairs, the Pre-Issue Checklist says so. Your certified inspector reviews and signs.