How do you prepare for an API 653 internal inspection?
Start with safety and records. API 653 clause 6.6 requires specific work procedures for the internal inspection that protect people and property, following clause 1.4: a hazard assessment and procedures built on API 2015 and API 2217A. Then pull the tank’s records and earlier reports, agree the bottom examination plan with the owner, and walk in with the Annex C out-of-service checklist.
Safe entry and cleaning
Clause 1.4 asks for an assessment of the hazards to people doing internal inspections, and procedures under API 2015 and API 2217A covering health and safety, fire and explosion, and damage to property. Follow the permit system; hot work needs a hot work permit (API 2009) outside areas designated safe for it; clause 1.4 also requires compliance with confined space regulations. The tank is emptied, cleaned and gas freed under the owner’s procedures before anyone enters. Special cases, such as gas freeing under the bottom, may need their own procedure.
Records to pull
- Construction records: nameplate data, drawings, specifications, material test results (clause 6.8.2).
- Inspection history: earlier reports, thickness readings and their locations, corrosion rate and interval calculations (clause 6.8.3). If the owner provides earlier reports and requires it, the new report must list the previous internal inspection dates, earlier areas of concern and the condition of earlier repairs (clause 6.9.2 b).
- Repair and alteration history, service changes and coating or lining records (clause 6.8.4).
- Earlier settlement readings, so the same points can be measured again (Annex B.2.1).
Plan the bottom examination
The internal inspection exists mainly to judge the bottom, gather thickness data for Section 4 and evaluate settlement (clause 6.4.1.1). Agree the MFL threshold with the owner before the scan: it is the least remaining thickness the scan must detect, and the owner sets it from the interval wanted (clause 4.4.5.1, NOTE 1). Confirm the NDE crew: UT thickness examiners need ASNT UT Level II full or limited certification under an approved procedure (clause 12.1.1.4), and API 575 Annex D gives guidance for qualifying MFL personnel and procedures (clauses 4.4.4 and 12.1.1.6). The authorized inspector supervises or does the visual examination and is answerable for the quality and completeness of the NDE results (clause 6.4.1.2).
Checklist
Annex C, Table C.2 is the sample out-of-service checklist (clause 6.7). Clause 6.9.2 also lists what the report must hold, such as the measured uncorroded thickness of at least one plate in each shell course and of each bottom plate, so it is worth reading before the job, not after.
Guided mode in TankForge
For a qualified inspector who is new to TankForge, a guided new-file wizard sets up the tank and builds a work list for the job. The guide then walks each step in order (tank info, team, layout, drawing, UT and MFL readings, photos, repairs, summaries, finish) with Prev / Next.
Also asked as
What is on an API 653 internal inspection checklist?
Annex C, Table C.2 gives a sample out-of-service checklist, item by item through the tank’s components. It is a sample; the owner’s program or the inspection company’s own list may add to it.
What should you bring to an out-of-service inspection?
The written safe-entry and work procedures, the tank’s construction records and earlier inspection reports, earlier thickness and settlement locations, the MFL threshold agreed with the owner, qualified NDE personnel and procedures, and the Annex C out-of-service checklist.
Does a tank have to be cleaned before an internal inspection?
For anyone to go inside, yes. API 653 clause 1.4 points to API 2015 for safe entry and cleaning; the tank is emptied, cleaned and gas freed under the owner’s permits first. The exception is an in-service bottom inspection with robotic tools under clause 6.4.1.2, where nobody enters.
TankForge is API 653 inspection software built by a working API 653 inspector. Draft report. Your certified inspector reviews and signs.