Question

What does it take to skip the hydrotest after a major tank repair?

Under API 653 clause 12.3.3, a major repair or alteration can go without a full hydrostatic test only when two things are true. First, an engineer experienced in storage tank design has reviewed and approved the repair and agrees in writing to taking the exemption, and the owner or operator has authorized it in writing (12.3.3.2). Second, the work meets the conditions in 12.3.3.3 through 12.3.3.6 that apply to it, or a fitness-for-service evaluation supports it (12.3.3.7).

Shell repairs (12.3.3.3)

  • Welding procedures for welds to existing metal are qualified on existing or similar material, with impact testing.
  • New material meets the current API 650 material requirements.
  • The existing material in the repair area meets at least one of: built to API 650 Seventh Edition or later; falls in the “safe for use” area of Figure 5.2; or the shell stress at the repair, from the fill height above the bottom of the repair, the diameter, the specific gravity and the thickness, is at or below seven thousand psi (forty-eight MPa).
  • New shell butt welds have complete penetration and fusion, the root and final passes are examined, and the finished weld is fully radiographed.
  • Nozzle neck and reinforcing plate welds have complete penetration and fusion; the back-gouged root and the completed weld get magnetic particle or liquid penetrant examination, and the completed weld also gets ultrasonic examination.
  • Door sheets do not reach the bottom-to-shell joint.

Bottom repairs in the critical zone (12.3.3.4)

The critical zone is the band of bottom or annular plate within three inches of the inside of the shell. Repairs there meet the same welding procedure and material conditions as shell repairs, are examined visually before welding, and get magnetic particle or liquid penetrant examination after the root and final passes. Annular plate butt welds also get ultrasonic examination after the final pass.

Shell-to-bottom weld repairs (12.3.3.5)

  • Any length of the weld may be replaced if the replacement meets the API 650 weld size and is no more than half of the required weld cross-section.
  • Or the weld on one side of the shell may be fully replaced for up to twelve inches; repairs that replace more than half the cross-section stay at least twelve inches apart, counting the other side of the shell.
  • Or, on a tank thirty feet in diameter or smaller that falls in the “safe for use” area of Figure 5.2, both sides may be fully replaced, or laid new during a bottom replacement.
  • In every case the repair is examined visually and by magnetic particle or liquid penetrant before welding, after the root pass and after the final pass.

Jacking and fitness-for-service (12.3.3.6, 12.3.3.7)

Minor shell jacking needs the shell and critical-zone material to meet one of the existing-material conditions above, and the engineer weighs the amount of jacking, toughness, quality control, inspection, temperature, foundation stability and the jacking method. A fitness-for-service evaluation is the other route; the standard gives no method or acceptance criteria, so it rests on the engineer who performs it.

Records

Keep the basis for the exemption with the tank records (clause 13.2): the engineer’s concurrence, the owner’s authorization, and the material, welding and examination records that show each condition was met.

The exemption in TankForge

The repair job card records the hydrostatic test decision. When the test is not performed under an exemption, the Pre-Issue Checklist reminds you to keep the engineer’s concurrence and the owner’s authorization on file. The draft report carries the decision and the clause; your certified inspector reviews and signs.